#CategoryDescriptionUnitQuantityRate (Rs)Amount (PKR)Action
1ExcavationEarthwork excavation in foundation trenchescft3,500Rs. 18Rs. 63,000
2PCC BedPlain cement concrete 1:4:8 under foundationscft1,200Rs. 280Rs. 336,000
3BrickworkFirst class burnt brick masonry in 1:5 cement sand mortarcft4,200Rs. 420Rs. 1,764,000
4RCC StructureReinforced cement concrete 1:2:4 in slabs, beams and columnscft3,200Rs. 580Rs. 1,856,000
5Steel RebarGrade 60 deformed rebar including cutting, bending & tyingkg8,500Rs. 285Rs. 2,422,500
6Plaster1/2 inch thick cement sand plaster 1:4 on interior wallssqft7,200Rs. 48Rs. 345,600
7FlooringPorcelain floor tiles 60x60cm with cement-bond adhesivesqft2,400Rs. 260Rs. 624,000
Subtotal:Rs. 7,411,100
Contingency (5%):+Rs. 370,555
Grand Total BOQ:Rs. 7,781,655