Total EstimateRs. 18,529,412Rs. 4,876 / sqft
Grey StructureRs. 16,461,60089% of total
Finishing CostRs. 5,198,40028% of total
Actual Cost SpentRs. 2,651,240Purchases + Labour
Project BudgetRs. 15,000,000Allocated Capital
Remaining FundsRs. 12,348,76082% unspent
Project Execution Health & Progress
Real-time engineering progress against procurement and financial burn rate
Overall Progress20%
Civil structure + finishes
Physical Work20%
First floor slab poured
Budget Consumed18%
Within 5% engineering tolerance
Procurement20%
Steel & cement secured
Estimated vs. Actual Cost Comparison
Civil & Grey MaterialsRs. 1,550,000 / Rs. 13,315,200
Labour Contracts & Daily WagesRs. 1,101,240 / Rs. 3,146,400
Total Project OutlayRs. 2,651,240 / Rs. 15,000,000
Next Milestones & Site Tasks
G+1 ScheduleGround Floor Slab Curing (14 Days)
Daily morning and evening water ponding
First Floor Brick Masonry
Target: 18,500 Awwal Bricks delivery
Sanitary Concealed Piping Inspection
PPRC pressure testing at 10 bar